April 2025 Update

  • building1729
  • 6 days ago
  • 1 min read

Site Development Plan (SDP) Round 2: Our Architects are hard at work addressing the second round of comments from the city. While these changes are being made, we are reviewing the project to do some basic value engineering - thereby ensuring that before our next step, we are poised to get the best and most beautiful campus built in the most financially efficient way possible!


Which leads us to....


Construction Documents: Once we have tweaked our plans for value engineering, our architects will be ready to start construction documents! (SDP focuses on everything outside the footprint of the building, while construction documents are the fine details inside the building.)


General Contractor: Based on the advice of our architects, we will wait until construction documents are 60-70% complete to bid out the project to general contractors to fine-tune our projected budget. At that point in time they will have a better picture of costs and the bids will be more accurate.

 
 
 

Recent Posts

See All
February 2025 Update

Address: DRUM ROLL PLEASE...... The city has designated an official address for our Shul property: 6523 E. Alaska Drive. This means that...

 
 
 
December 2024 Update

In the latter half of November, we received comments back from the City of Denver on our first "Site Development Plan" (SDP) submission....

 
 
 
October 2024 Update

Baruch Hashem, we have reached another major milestone! Our "Site Development Plan" (SDP) was submitted to the City of Denver right...

 
 
 